In September 2016, it was contracted by Shandong Jinjian for installation. Our company supplies mainframes, combustion systems, electrical instruments, etc.. The installation includes only ash storage and coal silos for commissioning and acceptance. The project passed the water pressure test on November 11, 2016, began commissioning on December 25, 2016, and completed the cold commissioning on January 7, 2017.